Structural and RCC works
Foundations, columns, beams and slabs executed to the structural engineer's drawings — with cube tests, bar-bending schedules and curing records kept for every pour.
OVERVIEW
The part of the building nobody sees and everybody depends on
Finishes can be redone. A structure cannot. That is why our RCC work is run as a controlled process rather than a trade: the drawing is checked before steel is cut, the formwork is inspected before concrete is ordered, and every pour leaves a record.
We take on the structural frame for new buildings, structural repairs and strengthening for existing ones, and steel structures for sheds and industrial roofs.
SCOPE
What we build
Foundations
Isolated and combined footings, raft foundations and pile caps built to the soil report and the engineer's design.
Columns, beams and slabs
The RCC frame, staircases and lintels — cast to the bar-bending schedule with cover blocks and checked reinforcement.
Formwork and steel
Plywood or steel shuttering aligned and plumbed, and reinforcement cut, bent and tied to the schedule.
Concrete quality control
Slump tests on every truck, cube samples for every pour, and a curing log you can inspect.
Repairs and retrofitting
Jacketing, crack injection, corrosion repair and strengthening for older or damaged structures.
Steel structures
Fabricated steel columns, trusses and purlins for sheds, warehouses and rooftop structures.
QUALITY CONTROL
How a pour is controlled
The same five checks before every slab, beam or footing.
- 01
Drawing and schedule check
Reinforcement is cut and bent to a bar-bending schedule prepared from the structural drawing and checked before tying.
- 02
Formwork inspection
Line, level, plumb, props and cover blocks are inspected by the site engineer and signed off before concrete is ordered.
- 03
Concrete verification
Delivery tickets checked against the specified grade; a slump test on every truck before it is accepted.
- 04
Cube sampling
Test cubes cast for every pour, labelled, cured and sent for testing; results filed with the weekly report.
- 05
Curing and de-shuttering
Curing logged daily; formwork removed only after the period set by the engineer, never to suit the programme.
Questions about structural work
Do you design the structure as well?
Structural design is done by a licensed structural engineer — yours or one we introduce — and we build to their drawings. Keeping design and execution separate is part of how the work stays honest.
Can you take over a half-built structure?
Often, yes. We start with a structural assessment of what exists — including testing where records are missing — and only then quote for completing it.
What records do I get?
Bar-bending schedules, pour records, slump and cube test results, curing logs and stage photographs. They are filed with the weekly reports and handed over at completion.
RELATED SERVICES
Often needed alongside this
Architecture & Planning
Floor plans, 3D elevations, structural design and GBA building plan approval — formerly handled under BBMP terminology — delivered with registered architects and licensed engineers.
ReadInterior Design
Layouts, ceilings, lighting and storage for houses and apartments, quoted item by item with the board, finish and hardware named rather than sold by the square foot.
ReadCommercial Interiors
Office, retail, showroom and clinic fit-outs, planned backwards from the date you need to open and built to the landlord's fit-out conditions.
Read
Have structural drawings ready?
Send them across and we'll price the frame from the bar-bending schedule and concrete quantities.