Plan sanction in Bangalore: a checklist before you build

Which authority sanctions your plan, what documents are usually asked for, the sequence to follow, and what to keep on site once work begins.

Why this matters more than it seems

Building without a sanctioned plan is the most expensive shortcut in Bangalore. Notices, demolition of unapproved portions, difficulty getting an occupancy certificate and problems at resale all trace back to it. The process is manageable if you start early and follow the sequence.

Which authority? Within the city's municipal limits, building plans are sanctioned by the Greater Bengaluru Authority — the body that replaced the BBMP in 2025, now operating through five city corporations. Sites in BDA-formed layouts have their own requirements, and plots in surrounding village limits fall under the local panchayat or the planning authority notified for that area. Your architect or licensed engineer confirms which applies to your survey number.

IN ORDER

The approval sequence

  1. 01

    Verify title and khata

    Confirm the sale deed, khata certificate and extract, tax receipts and encumbrance certificate are in order. Approval starts with clean paperwork.

  2. 02

    Appoint a registered architect or engineer

    Drawings must be prepared and signed by a professional registered with the authority. This is also who submits the application.

  3. 03

    Prepare drawings to the bylaws

    Setbacks, floor area ratio, height and parking follow the plot size and road width. Drawings are prepared to comply, not adjusted afterwards.

  4. 04

    Submit and pay fees

    The application, documents and fees go through the authority's process. Queries are answered by your architect.

  5. 05

    Sanction and commencement

    Once sanctioned, the approved plan and commencement certificate are issued. Only now does excavation start.

  6. 06

    Build to the sanctioned plan

    Keep a copy on site. Deviations create problems at completion; changes go through a revised sanction.

  7. 07

    Completion and occupancy

    On completion, the occupancy certificate application confirms the building matches the sanctioned plan. Keep it with the title documents.

DOCUMENTS

What is usually asked for

The exact list depends on the authority and your plot. This is what most applications include.

What is usually asked for
DocumentWhy it's needed
Sale deed and title documentsProves ownership of the plot being built on
Khata certificate and extractConfirms the property is recorded with the authority for tax purposes
Latest property tax paid receiptShows dues are cleared
Encumbrance certificateShows the property is free of registered claims for the period requested
Survey sketch or site planFixes the plot boundaries and dimensions the drawings are based on
Building drawings by a registered professionalThe plan being sanctioned, prepared to the bylaws
Structural stability certificateUsually required as the number of storeys increases
No-objection certificates where applicableFire, airport height limits or utility providers, depending on the site and building

What to keep on site once work starts

  • A copy of the sanctioned plan, with the sanction number visible
  • The commencement certificate
  • Any approval letters or NOCs the sanction depended on
  • A site register recording inspections and visits

Questions about approvals

Can you get the plan sanctioned for me?

Sanction applications are submitted by the registered architect or engineer who prepared the drawings. We coordinate closely with them and build to what is sanctioned; if you don't have one, we can introduce independent professionals.

What happens if the building deviates from the plan?

Small deviations may be regularised through a revised sanction; larger ones can attract notices or be refused an occupancy certificate. It is far cheaper to revise the plan before building than to fix the building after.

Do I need an occupancy certificate?

It confirms the completed building matches the sanction and is the document buyers, banks and utilities increasingly ask for. Plan for it from the start.

WHO DOES THIS FOR YOU

The service behind this guide

  • Architecture & Planning

    Floor plans, structural design and GBA building plan approval — formerly handled under BBMP terminology — filed in your name by registered architects and licensed engineers.

    Read
  • House Construction

    Once the plan is sanctioned, the build itself: from the soil test to the keys on one itemised contract.